"No damages for delay" clause bars recovery in CDRB case.
A contractor hired to install equipment on the Staten Island Ferry sought
additional payment of $90,389 to cover extra performance and payment bond
premium costs incurred because the contract term was extended to keep
the ferry fleet in operation.
Radio Holland USA, Inc. v. Dep't of Transportation
(in PDF), OATH Index No. 629/12, mem. dec. (Feb. 9, 2012).