THAT SHIP SAILED

benchnotes_oath.gif

Contracts

"No damages for delay" clause bars recovery in CDRB case.

A contractor hired to install equipment on the Staten Island Ferry sought additional payment of $90,389 to cover extra performance and payment bond premium costs incurred because the contract term was extended to keep the ferry fleet in operation.

Radio Holland USA, Inc. v. Dep't of Transportation (in PDF), OATH Index No. 629/12, mem. dec. (Feb. 9, 2012).